Pacific Park Artificial Turf Field Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Scope

The project was originally designed to convert the natural turf ballfield at Pacific Park into a multipurpose artificial turf field.  On June 28, 2022, the City Council adopted a motion to change the scope of this project and proceed with natural turf as the choice of surface for the field. The revised project scope will include excavation of existing grass and 6-8 inches of soil, installation of a new drainage system, new catch basins for water percolation, incorporating new balanced soil, installation of irrigation system, laser grading, sod installation, installation of new bases, extending the fences as in the original scope of work, and completion of the ballfield layout.

Budget

The budget for this project is $1,017,042, in CDBG funds.

Status Update

David Volz Design, Inc. (Consultant) provided a revised proposal of $49,863 to update the drawings for natural turf.  DVD has nearly completed 90% of the design, and permitting submittal is expected by July/August 2024.  Project is anticipated to be completed by Summer/Fall 2025.

Pacific Grass Field