Project Scope
Project scope includes adding shade structures over both the 2-5 year old preschool-age and 5-12 year old school-age playgrounds, as well as a new shade structure at the Pacific Pool deck area. It also includes design and replacement of the existing splash pad with a new enhanced water play area with water treatment and recycling system to conserve water use. The restroom is also being redesigned to enhance safety, and the pool has been replastered.
Funding
The current construction budget is $3,041,173 in CDBG ($1,552,653), Development Impact Fees ($731,322), Measure S ($300,000), and CIP Funds ($457,198).
Status Update
Work at the pool has been mostly completed and opened to the public again mid-June, with the pool replastering, deck cleaning, and new concrete deck areas already completed. Construction at the playground is also well underway, with the playground nearly completely installed and the splash pad being installed in July 2024. The restrooms and shade canopies will be finished in August, and the project is anticipated being finished and open in November 2024.
Portable restrooms and handwash sinks have been made available during construction. The Community Center’s lobby restrooms are also available but only during standard hours of operation, which are Monday through Thursday, 9 AM to 9 PM, and Friday and Saturday from 9 AM to 5 PM.