Home MenuArden Avenue Rehabilitation Project
Construction Period
Expected Schedule: August 18, 2014 - End of November 2014
Scope of Work
- Repair of the existing sewer main pipe line at various locations;
- Grinding of existing pavement;
- Selective removal and replacement of deteriorated asphalt concrete pavement;
- Selective reconstruction of curbs, gutters, driveways, cross gutters, and alley aprons, sidewalks;
- Overlay pavement with rubberized asphaltic concrete pavement;
- Planting new 24-inch box trees, and
- Installing pavement markings.
Project Location
Arden Avenue Between Highland Avenue and Kenilworth Avenue. View/Download Map
All Construction Notification to Residents
Construction Photos:
Contact
- General Contractor: Toro Enterprises Inc. (805) 432-0078
- Public Works Engineering Division: (818) 548-3945
- Public Works Engineering Division Project Manager: Saumil M. Mody, email