Glendale Avenue Wastewater Capacity and Street Improvement Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option
Construction Schedule

Construction is scheduled to begin in May 2014 and be completed by January 2015 barring adverse weather conditions. The sewer work will be completed during the school summer break and pavement work in fall 2014.

Current Construction Status

  • Paving work will occur in 5 phases on Glendale Avenue between San Fernando Road and Broadway Street will begin on Monday, October 27, 2014- Tuesday, November 18, 2014. One traffic lanes will be closed in each direction during paving work. Access may be restricted from 7:00 am-7:00 pm. Street parking will not be allowed during the construction hours and temporary no parking signs will be posted in advance for enforcement.
  • Pavement Grind -October 27, 2014- October 31, 2014
  • Cold-In-Place (CIP) Recycling Existing Pavement Base- November 3, 2014- November 7, 2014
  • Re-roll of (CIP) Pavement Base - November 12- November 13, 2014
  • Place Leveling Pavement on Side Streets- November 10, 2014
  • Place Rubberized Pavement Surface Course - November 13, 2014- November 18, 2014

Project Location

Project Location Map
Scope of Work
  • Upsizing of the existing sewer main pipe line between Chevy Chase Drive and East Maple Street
  • Repair of the existing sewer main pipe line at various locations;
  • Selective repair of damaged concrete curbs, gutters, driveway aprons, sidewalks, curb ramps, cross gutters, alley aprons and bus pads;
  • Grinding of existing pavement and Cold-in-Place rehabilitation of existing asphalt pavement base
  • Overlaying base pavement with rubberized asphalt pavement;
  • Modification of traffic signals;
  • Removal of in-roadway pedestrian warning lights and installation of pedestrian flashing beacons
  • Installation of striping and pavement markings.
All Construction Notification to Residents
Community Meetings
A community meeting for the Glendale Avenue Wastewater Capacity & Street Improvement Project was scheduled for Thursday, November 21, 2013 at 6:00 PM at Glendale City Hall - Council Chambers, 613 E Broadway,  Glendale, CA, 91206. Click here to view the PDF version of the Powerpoint Presentation.

 Glendale Ave Comm Meeting

Contact

  • Public Works Engineering Division: (818) 548-3945
  • Public Works Project Manager: Jasmina Zigic (818) 937-8255, Email
  • Contractor: Excel Paving Company: Project Manager: Jason Martin,  Phone 562-599-5841

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer