The Citywide Battery Backup System (BBS) project exemplifies its commitment to public safety. Implementing cutting-edge BBS technology at 65 signalized intersections, it aligns with California Department of Transportation standards, ensuring continuous operation during power outages. Prioritizing reliability and resilience, it significantly enhances road safety, benefiting all users and improving Glendale's transportation infrastructure. Seamlessly integrating BBS technology into existing signal cabinets showcases innovative planning and construction, minimizing disruptions while maximizing efficiency. Testing BBS post-installation, without affecting traffic flow, underscores the project's commitment to uninterrupted service during outages. Funded by METRO Measure R, this BBS project combines extensive coverage, high standards, innovative methods, and rigorous testing, setting a commendable standard for Glendale's transportation infrastructure.

traffic signal installation

Scope of Work

  • Installation of new traffic signals
  • Installation of new curb ramps to meet current Federal Americans with Disabilities Act (ADA) requirements;
  • Installation of new striping and pavement markings;
  • Installation of new battery backup systems and upgrade of existing battery backup systems (see Exhibit 2: Battery Backup System Location Map);
  • Installation of rectangular rapid flashing beacons, and;
  • Railroad Quiet Zone Safety Improvements, such as security fencing, handrails, and minor striping

Schedule

May 2016 to October 2016

Construction Locations 

  • Broadway and Kenwood Street
  • Broadway and Everett Street
  • Chevy Chase Drive and Harvey Drive
  • Verdugo Road and Glencoe Way
  • Verdugo Road and Sunview Drive
  • Colorado Street and Lincoln Avenue
  • Grandview Avenue Railroad Crossing
  • Sonora Avenue Railroad Crossing

Exhibit 1 Location Map

Exhibit 2 Location Map

Updates

Construction at Broadway and Kenwood Street currently, expect minor delays

Construction Notification

Contractor Letter

Contact Information

·  Public Works Engineering, (818) 548-3945

·  Project Manager, Sarkis Oganesyan (818) 548-3945, Email

·  Project Manager, Marc David (818) 548-3945, Email

·  Contractor: Vart Construction, Inc. (818) 618-2023