Palmer Avenue and Green Street Rehabilitation Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project location: 

Scope of work:

  1. Surface grinding and placement of approximately 2.0 centerline miles of ARHM
  2. Selective removal, repair, and reconstruction of approximately 1,500 linear feet of damaged curbs and gutters, and 5,500 square feet of sidewalks, driveways, cross gutters, alley aprons, and bus pads
  3. Modification and reconstruction of approximately 10 existing curb ramps to meet current ADA standards
  4. Adjustment of existing manholes and water meters to finished grade
  5. Removal and replacement of existing traffic striping and pavement markings
  6. Realignment and upgrade of Adams Street and Palmer Avenue intersection

Construction schedule:

Project completed September 2024

Construction photos:

Palmer Ave_07 (002)

Contact information:

Public Works Engineering: 818.548.3945

Public Works Project Manager: Marc David, mdavid@glendaleca.gov