City of Glendale, CA
Home MenuTraffic Signal Installation and Modification at Various Locations and Broadway-Brazil Grade Separation
Scope of Work
The work generally includes:
- Installation and modification of 6 traffic signals;
- Fiber optic communication installation;
- Surface grinding and placement of ARHM and Asphalt Concrete Pavement (Leveling Course);
- Construction of Portland Cement Concrete ADA curb ramps, and
- Installation of striping and other pavement markings
Construction Schedule
Construction began in October 2018 and is expected to finish by September 2019.
Project Location
New traffic signals will be installed at the following intersections:
1. Pacific Avenue at Glenwood Road
2. Chevy Chase Drive at Windsor Road
Existing traffic signals will be updated by the latest Caltrans standards at the following intersections:
1. La Crescenta Avenue at Montrose Avenue
2. La Crescenta Avenue at Honolulu Avenue
3. Central Avenue at Chevy Chase Drive
4. Broadway/Brazil Street at San Fernando Road
Click Here for Project Location Map
Contact
- Public Works Engineering: (818) 548-3945
- Project Manager: Sarkis Oganesyan, Email / Marc David, Email