Glendale-Los Angeles Garden River Bridge Project (Glendale Narrows Riverwalk, Phase III)

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Glendale-Los Angeles Garden River Bridge Project (The Glendale Narrows Riverwalk Project – Phase III)

The Glendale Narrows Riverwalk runs along the north bank of the Los Angeles River opposite Griffith Park from Bette Davis Park past DreamWorks Studios to the 134 Freeway.  With the completion of Phase III, the Riverwalk will provide approximately 1 mile of trails for bicyclists and pedestrians that will include parks, rest areas, river overlooks, an equestrian facility, interpretive signage, a public art project, and a bridge connecting Riverwalk to Griffith Park and/or North Atwater.  Initially opened to the public in 2012, there is currently a mile of recreational trail, two parks, public art installations and an equestrian facility. 

The Garden River Bridge consists of a two-span curvilinear structure with two canopied seating areas. The seating areas and views of the river offer a continuation of the parks on the Glendale and Los Angeles sides of the river, with the canopies providing shading and space to enjoy the river environment. It is possible to have solar paneling or planting over the canopies. Lighting will be incorporated to enhance the user experience and make the structure a landmark viewed from the parks or the adjacent freeways.

The Garden River Bridge will be an extension of the Riverwalk parks and provide a space for users on the bridge to enjoy the river. Two planted seating areas in large overlook areas are featured, offering views of the river. The curves in the bridge add to this experience.

The Glendale-Los Angeles Garden River Bridge project will be funded by Proposition “C”, Measure R Sub-Regional Highway, and Proposition 68. Please click here, or visit www.gardenriverbridge.com for more information.

Project Location

  • Click here for Project Location Map

Project Schedule

Milestone

Duration

Anticipated Completion Date

Environmental Document

18 months

June 2023

Pre-Design Phase

2 months

February 2022

Schematic Design Phase

3 months

May 2022

Design Development Phase

4 months

September 2022

Construction Documents – 50% Completion

10 months

July 2023

Construction Documents – 90% Completion

12 months

July 2024

Construction Documents – 100% Completion (Permits Ready to Issue)

12 months

July 2025

Bid and Award Phase

6 months

February 2026

Construction

24 months

December 2027

Post-Construction

6 months

February 2029

 

Phase

Design

Project RFP 

For more information regarding this project's Request for Proposal (RFP), please click here

Riverwalk Photos

             Riverwalk_Pic 1

 

 

Riverwalk_ Side Tour

 

Community Meetings

Riverwalk Comm Mtg 2

Contact

  • Public Works Engineering Division: (818) 548-3945
  • Public Works Project Manager: Sarkis Oganesyan, Email