Montrose Park Parking Lot Reconstruction and ADA Improvements Projects

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Scope of Work

  1. Remove and Replace Upper Parking Lot Pavement
  2.  Selective concrete removals and replacement in the Upper Parking Lot area
  3.  Upgrade of new underground conduit infrastructure in the Upper Parking Lot area
  4.  Installation of new striping and curb markings

Construction Schedule

  • Project construction was completed on September 9, 2021. 

Construction Updates

  • Contractor Mobilization August 16, 2021. 

Traffic Impacts

  • Upper Parking Lot will be temporarily closed due to project improvements. Concrete walking paths will be temporarily affected during concrete removal and replacement. 

Project Location

Project Location Image

Construction Photos

  • Please check back at the start of the project.

Contact Information

  • Public Works Engineering, (818) 548-3945
  • Public Works Project Manager: Marc David, Email